The project to expand the capacity of the desalination plant "Kaspiy" in Aktau

English
Technical director of the contractor company Sergey Mikotin, who is leading the project to expand the capacity of the Kaspiy desalination plant in Aktau, shared details about the work being carried out, the press service of the Mayor's Office of the city reports.
"Testing is currently underway to launch new plant facilities. The first tests were completed successfully. The next stage of testing will begin on Saturday and will last 72 hours. Then, the operation of the installations will be temporarily suspended to check the technical regulations of operation. If all indicators comply with the standards, it is planned to launch two installations, which will ensure the supply of 10,000 cubic meters of water to the city in normal mode," said Sergey Mikotin, technical director of the contractor company.